Refinery Production (Crude Throughput) during the month of Feb, 2016
Production During the
PSU /Private CO
Undertaking / Unit
Refinery Production
Month under review*
Feb
2016
Production During the
Corresponding month last year
Feb
2015
Preceding month of current year
January
2016
Cumulative Production
Actual Prodn. During current year
Apr-Mar
2015-2016
Actual Prodn. Corresponding period last year
Apr-Mar
2014-2015
(In terms of crude)
Public Sector 10563.29 9656.61 21165.36 41279.58
IOC, Guwahati 37.80 71.17 95.26 90.92
IOC, Barauni 506.44 457.61 527.14 404.10
IOC, Koyali 1177.50 1037.22 1204.39 1121.74
IOC, Haldia 640.62 600.28 662.71 669.43
IOC, Mathura 739.98 648.21 700.13 686.95
IOC, Digboi 44.03 46.29 55.19 55.57
IOC, Panipat 1296.63 1108.89 1366.43 1279.42
IOC Bongaigaon 191.73 199.86 230.73 230.39
Total IOC 4634.73 4169.53 0 4841.98 4538.52
BPCL, Mumbai 1119.30 1034.50 1163.69 1151.19
BPCL, Kochi 872.64 838.61 928.15 838.14
Total BPCL 1991.94 1873.11 0 2091.84 1989.33
HPCL, Mumbai 695.80 633.58 419.21 624.72
HPCL, Visakh 782.71 727.62 807.39 780.33
Total HPCL 1478.51 1361.2 0 1226.6 1405.05
CPCL, Manali 867.67 800.01 907.24 851.75
CPCL, Narimanam 54.62 38.26 43.32 41.85
Total CPCL 922.29 838.27 0 950.56 893.6
NRL, Numaligarh 203.01 216.38 150.79 226.26
MRPL, Mangalore 1325.63 1193.97 1336.10 1251.63
ONGC, Tatipaka 7.19 4.15 4.21 5.24
Joint Venture Sub Total 1201.80 1003.65 2698.06 5246.09
BORL, Bina 502.20 465.27 571.14 592.24
HMEL, Bhatinda 699.60 538.38 925.13 901.00
Private Sector $ 7236.20 6924.97 14844.04 24853.52
RPL, Jamnagar 2578.04 2498.97 2740.21 2703.61
RIL, SEZ 2988.17 2827.69 3104.02 3004.00
Essar Oil (EOL), Vadinar 1669.99 1598.31 1763.61 1694.58
TOTAL 19001.29 17585.23 0 38707.46 71379.19